DC Vint Hill,VA: huge work, you're the best guys
DC Vint Hill,VA: huge work, you're the best guys! The first racks are UP. Close to start the «private beta» in Virginia,US :)
DC Vint Hill,VA: Guard house concrete pad is done
DC Strasbourg
DC Strasbourg
FR: SBG1/2/4 is closed to be full
SBG3 is ready in 2 months
FR: SBG1/2/4 is closed to be full
SBG3 is ready in 2 months
Network Maintenance, 22nd June
We are writing to inform you of some network maintenance which needs to be carried out this Thursday the 22nd of June, at 5 am. Please find all the details of the intervention below:
Background
To improve our services, since the 6th of June 2017, we have been gradually switching some networks to new routers, especially those using our BHS-3A and BHS-3B routers.
Current situation
Due to a software malfunction on one of the network cards, which was beyond our control, the previous settings have not changed. We therefore need to force the routing to the new equipment, by entering configuration commands.
We also need to update the BHS-3B chassis to make sure that these instructions are registered correctly.
Intervention
To ensure minimal impact, the intervention is scheduled to take place during a period of low traffic: Thursday the 22nd of June at 5 am.
The upgrade is due to take approximately one hour. All the servers will then be routed via BHS-3A, with a possible slight reduction in speed.
Rest assured that we have put all the necessary measures in place to limit any impact on your services.
Please do not hesitate to contact us for any further information.
The OVH team
Background
To improve our services, since the 6th of June 2017, we have been gradually switching some networks to new routers, especially those using our BHS-3A and BHS-3B routers.
Current situation
Due to a software malfunction on one of the network cards, which was beyond our control, the previous settings have not changed. We therefore need to force the routing to the new equipment, by entering configuration commands.
We also need to update the BHS-3B chassis to make sure that these instructions are registered correctly.
Intervention
To ensure minimal impact, the intervention is scheduled to take place during a period of low traffic: Thursday the 22nd of June at 5 am.
The upgrade is due to take approximately one hour. All the servers will then be routed via BHS-3A, with a possible slight reduction in speed.
Rest assured that we have put all the necessary measures in place to limit any impact on your services.
Please do not hesitate to contact us for any further information.
The OVH team
New OVH IP ranges
New OVH IP ranges: 54.36.0.0/14 and 145.239.0.0/16
DC Strasbourg,FR: 4th floor of SBG3
Let’s ship new ASR9904 and N7706 for 100G backbone on US WestCoast
Let’s ship new #ASR9904 and #N7706 for #100G backbone on US WestCoast
And the third 100G upgrade for LosAngeles
And the third 100G upgrade for LosAngeles is ready now
ASR/N7 with 4x100G capacity but with #RSP-880-SE
ASR/N7 with 4x100G capacity but with #RSP-880-SE
DC Strasbourg,FR: SBG3
DC Strasbourg,FR: lot of cables to connect the DC SBG3 to the power 20KV and the network's backbone